Table I       Summary of the three major recommendation directions



                 Speed         Large-scale developments          Private housing developments        Public housing developments
                   up
                           1.   Simplify public engagements and   6.  Release Comprehensive Development Areas   12.  Make proactive and professional
                              Environmental Impact Assessment   •  Divide Comprehensive Development Areas into   judgments during district consultations
                              procedures                          smaller sites according to size and ownership   •  Recognise the consultative functions of the
                              •  Simplify and consolidate public engagement   distribution              District Council, and instruct departments to
                                under various ordinances        •  Establish precise and quantifiable approval criteria   respond to relevant feedback with
                              •  Broaden the definition of minor works to   for Master Layout Plans     professional judgment to proceed swiftly to
                                simplify land gazetting process   7.  Enhance town planning procedure   the next phase
                              •  Shorten environmental survey and report   •  Shorten the time required for the town planning   13.  Draw reference from the practice of the
                                production time, and define clear objectives   procedure              past Private Sector Participation Scheme
                                for each evaluation criteria
                                                                •  Rationalise arrangements under the town planning   to improve construction efficiency
                           2.  Proceed with reclamation works and   procedure                         •  State sizes and quantities of residential units
                              town planning procedure simultaneously  8.  Accelerate urban redevelopment  in tender documents
                              •  Divide development projects into reclamation   •  Introduce measures to accelerate private   •  The Housing Authority or Hong Kong
                                and superstructure development for   redevelopment projects, such as lowering the   Housing Society can randomly select some
                                reclamation works and town planning   threshold for compulsory sales, exploring the   of the completed units for repurchase at a
                                procedure to proceed simultaneously  transfer of plot ratio, raising plot ratio in some   predetermined price
                                                                  urban areas, street consolidation, and
                           3.  Accelerate land assembly to unleash the   interchangeability between residential and   14.  Enhance transparency and
                              development potential of private lands  nonresidential plot ratios      accountability of public housing projects
                              •  Study on various land assembly models  •  Reflect the corresponding changes in the Outline   •  Establish a “one-stop” platform to disclose
                              •  Establish a new mechanism to unleash the   Zoning Plan following the research by the Urban   the progress of various public housing
                                development potential of Tso/Tong lands  Renewal Authority, and adopt a more flexible   projects
                                                                  compensation strategy               •  Formulate public housing supply schedules
                           4.  Commence detailed designs in all                                         for the next 10 years
                              phases in parallel             9.  Simplify land leases
                              •  Begin land resumption and clearing works in   •  Exclude specific requisites if they are already
                                advance                           covered in relevant regulations or overseen by
                              •  Adopt targeted measures for various   other departments
                                occupiers to smoothen the resumption   10.  Accelerate lease modification procedure
                                process
                                                                •  Extend the use of “standard rates” to all lease
                           5.  Appoint developers to build some   modification applications for agricultural lands in
                                                                  the New Territories
                              infrastructures to bring forward private
                              development projects scheduled for later   •  Establish a clear timeframe for reviewing and
                                                                  approving lease modifications
                              phases
                              •  Initiate land exchange procedures for private   11.  Strengthen the functions of the Development
                                lands in the remaining phases during phase 1  Projects Facilitation Office
                              •  Introduce an appropriate mechanism in land   •  Serve as a decision-making body that coordinates
                                exchange to entrust developers with road   land development approval works and aptly
                                construction near private developments  balance the requirements from different
                                                                  departments
                                                                •  Act as the first and only point of contact between
                                                                  the Government and developer